Road construction work in the Nürburgring area

04.05.2026

Due to several construction and renovation projects, traffic restrictions are currently in place on major roads around the Nürburgring. Please take this into account when traveling to the area and follow the posted detours. We have compiled the most important information for you below. For further details, please visit the website of the Rhineland-Palatinate State Mobility Agency.

B 257 - Asphalt work in the town of Müllenbach continues due to weather conditions
The asphalt work underway since March 18 in the town of Müllenbach along the B 257 is expected to continue beyond March 31. This is due to the weather conditions forecast for the coming week, which are not expected to allow for the asphalt to be laid as scheduled.

The work will therefore be postponed by approximately two weeks. As soon as weather conditions permit, the asphalt will be laid immediately.

For the duration of the work, the affected section of the road will remain fully closed. During this time, traffic will be diverted from Wiesemscheid via the B 258 toward the Nürburgring, via the L 94 toward Welcherath, and via the B 410 toward Kelberg. The town of Müllenbach can only be accessed via Kelberg during the construction period.

ℹ️ The detour is clearly signposted on site.

L 93 – Road resurfacing between Müllenbach and the Nürburgring has begun
Since March 24, the L 93 between Müllenbach and the Nürburgring has been undergoing extensive resurfacing. For structural and safety reasons, this work can only be carried out under a full closure.

During this time, traffic will be diverted over a wide area via the B 257 toward Kelberg, and from there via the B 410 toward Hünerbach, connecting to the K 89 and L 94.

Local traffic to the ADAC Driver Safety Center at the Nürburgring will be maintained via a temporary access road. The schedule for the asphalt work will be coordinated in advance with the Driver Safety Center to adjust operational procedures accordingly.

Following the road resurfacing, the guardrail system will be completely replaced. For this work, a single-lane closure with traffic light control is planned.

ℹ️ Current information on this, particularly regarding traffic routing, can be found in the Mobility Atlas at here.